Underway
Baltic-Green-NET
The project 24-EU-TG-Baltic-Green-NET, with the project title: Shore-side electricity for RoRo/RoPax vessels on green corridors in the Baltic Sea, has received funds from the Alternative Fuels Infrastructure Facility (AFIF), running under the Connecting Europe Facility (CEF).
The Port of Trelleborg is the coordinator of the project, developed together with the port of Lübeck-Travemünde. The aim is to establish a network of green corridors and shipping links in the Baltic Sea, by deployment of shore side electricity supply for RoPax and RoRo vessels.
The main objective is to improve operations and sustainability in two TEN-T core ports in Sweden and Germany. A total of six berths will be equipped with onshore power supply (OPS): two berths in the port of Trelleborg (Sweden) and four berths in the port of Lübeck-Travemünde (Germany). Part of the supplied energy will be produced by two wind turbines, to be installed in the port of Lübeck-Travemünde within the project. In the Port of Trelleborg, two large wind turbines are previously deployed.
The investments in the Port of Trelleborg include works for the completion of onshore power supply at two berths, including connection to the grid and testing.
The works are performed at ferry berths no. 10 and 11, at the port power station behind berths no. 8-9 and in-between. The deployment of the required installations includes:
- Power distribution station with high voltage;
- All necessary connections and ducts, adaptation works;
- Cables and cable management systems at two berths;
- Energy measuring systems and integration by the port system interface.
The works in the port of Trelleborg will be completed during Q1 2026. The port will continue to supervise and coordinate the remaining investments in the port of Lübeck-Travemünde, which aims to achieve a gradual completion of the planned installations util March 2027.
The project extends between November 2024 – March 2027.
Rail-IT
The project “Rail-IT” (Rail-IT-MoS) is a collaborative project between the Port of Trelleborg and the Port of Rostock, where we have been granted co-financing from the EU Commission’s fund for a connected Europe (Connecting Europe Facility – CEF) and the priority area “Motorway of the Sea” (MoS). Also in this project, Port of Trelleborg acts as coordinator due to our successful experience with similar co-financed EU projects.
The main focus of the project is to improve and develop the transport corridor between Trelleborg and Rostock with a specific focus on the development of the railway in the Port of Rostock and the completion of areas with associated IT equipment in the Port of Trelleborg.
The following activities are included in the project on behalf of the Port of Trelleborg:
– The completion of surfaces in the eastern part of the Port of Trelleborg
The project extends between January 13, 2023 and December 31, 2025
Blue Supply Chains
The Port of Trelleborg participates in a so called “Interreg project” together with Hamburg Marketing, Port of Rostock and Stena Line, where together they will develop the already existing transport chain between Trelleborg and Rostock with a focus on low emissions.
Stena Line will focus on optimizing its rail ferry traffic between Trelleborg and Rostock. The Port of Trelleborg and the Port of Rostock will each carry out a capacity analysis on the current railway within the respective port, with the aim of increasing green intermodal terminal handling.
The project extends between January 1, 2023 and December 31, 2025.
Digi MoS
In our project “Digi MoS” (Optimization and greening of traffic flows on the TEN-T corridors connecting Scandinavia and the continent), Port of Trelleborg together with “Lubecker Hafen”, “Lubeck Port Authority” and “TT-Line”, have been granted co-financing from the European Commission’s fund for a connected Europe, the Connecting Europe Facility (CEF) and the priority area “Motorway Of The Sea” (MoS). In this project, the Port of Trelleborg acts as coordinator as we are the party with the highest investment in the project.
The project’s main focus is to improve and develop the transport corridor, where the activities are part of the long-term digital and environmental work that the Port of Trelleborg is continuously working on.
The following activities are included in the project on behalf of Port of Trelleborg:
1) Optimization and adaptation of the side ramp in ferry berth no. 10 to accommodate the new enlarged LNG-powered vessels from TT-Line
2) Optimization and adaptation of the side ramp in ferry berth no. 13 to accommodate the new enlarged LNG-powered vessels from TT-Line
3) Streamline the trailer handling for Port of Trelleborg as well as for its customers
4) Installation of new cameras and measuring equipment to improve traffic flows in Port of Trelleborg
The project extends between January 1, 2021 and December 31, 2025.
Green FIT 2025
Port of Trelleborgs project “Green FIT 2025” was one of six projects that was granted co-financing from the European Commission’s fund for a connected Europe, Connecting Europe Facility (CEF).
The project goes by the working name “Green FIT 2025” (Clean and efficient multimodal hub in Port of Trelleborg) and runs until 2024. “Green Fit 2025” aims to continue the expansion and port relocation that began in 2012 to the southeast.
The following activities are included in the project:
1) Construction and validation of 2 new large ferry berths (no. 11 and 12)
2) Installation of two wind turbines in the port to provide electricity to ships
3) The construction of a wastewater reception facility and a treatment plant to support waste management
4) Improved handling of intermodal trains and rail connections
The project extends between January 1, 2021 and September 30, 2025.
REDII Ports
Port of Trelleborg will conduct a study on the future capacity need for truck charging stations in port, considering the investment and development plans of relevant manufacturers as well as the haulers’ plans for replacing current truck fleets with new ones running on green fuels. Based on a set of indicators/market factors, a model to estimate the charging needs and infrastructure needed in ports will be realised. This will be turned into an open-source planning tool for all ports to use to meet the requirements of, e.g., the Fit-for-55-package. The tool will also be able to reversely predict the scope 3 emissions reductions that can be achieved by a certain amount of green charging, thus aiding ports in setting science-based targets.
The project will receive financial support from the Interreg North Sea Programme.
The project extends between September 20, 2022 until March 2026.